BOREHOLE
DRILLING & EQUIPMENT QUOTATION
|
Preriminary Works
|
|
|
|
| |
Description
|
Unit
|
Qty
|
Rate
|
Total( Kshs)
| |
|
|
|
|
| |
Geological Survey
|
|
|
|
| |
Geological survey including preparation of the report and submission to the Water resources management Authority (WRMA) for purposes of Authorization. This includes WRMA Fees and following up of the issuance. |
Ls
|
1
|
65,000
|
65,000
| |
| |
|
|
|
|
| |
Enviromental impact assement.
|
Ls
|
1
|
35,000
|
35,000
| |
EAI Survey and report including Submission to the National
Environmental management
Authority (
NEMA)
| |
|
|
|
|
| |
Local authority
|
|
|
|
| |
Application of all local Authority and user associasion
letter of no objection
|
Ls
|
1
|
20,000
|
20,000
| |
Sum Total
|
|
|
|
120,000
| |
|
|
|
|
| |
Borehole Drilling
|
|
|
|
| |
Mobilization
and demobilization
|
|
|
|
| |